The construction of 190km double-lane road between Tanzania/ Morogoro - Dar es Salaam has been successfully completed. The contract price of the project is 114,000,000 USD. The project began in 2016 and was completed ahead of schedule and successfully in 2018.
Completed works include:
Construction of 152km double-lane 30cm asphalt surface asphalt road
Construction of 5.5km main feeder road with 20cm asphalt road
Construction of 6km main feeder road with 20cm asphalt road
Construction of 7km main feeder road with 20cm asphalt road
Construction of 7.5km main feeder road with 20cm asphalt road
Construction of 2.5km feeder road with stabilize road
Construction of 4.5km feeder road with stabilize road
Construction of 5km feeder road with stabilize road
Precast intersection bridge crossing
Precast bridge and 4 culvert structures
Construction of 6 14km culverts and reinforced concrete trenches